Framework Agreement for the Solar Park - Energielandschap Lageland
Omschrijving van de opdracht
The Client intends to enter into a Framework Agreement (the Agreement) with three (3) parties for the construction of the Solar Park.
The Specific Contracts under the Agreement will be put out to tender as turnkey EPC contracts for the Solar Park, with the Tenderer who, in the ranking of this tender, has submitted the most economically advantageous tender being awarded the first Specific Contract. The EPC contractor must deliver the solar park on a turnkey basis, including the intake substation. The EPC contractor is responsible for the necessary coordination with the supplier of the intake substation and for ensuring the correct integration of both installations.
Phase 1: approximately 58.9 MWp PV, connected to a 21 MW grid connection (shared with the BESS), with a target operational date of Q1
Phase 2: expansion by approximately 142.3 MWp of PV (total approximately 201 MWp; including third-party contributions, approximately 250.5 MWp), in conjunction with the upscaling of t 2029.
Vakgebieden
CPV-codesAanbestedingsstukken
13 documentenOfficiële publicatie: bekijk de aankondiging op TenderNed →
Werk je aan de volgende inschrijving?
Bekijk welke aanbestedingen nu open staan en stel je inschrijving met je team op één plek samen.
Aanbesteding van Zonnepark Meerstad Noord B.V.
"Framework Agreement for the Solar Park - Energielandschap Lageland" is een aanbesteding van Zonnepark Meerstad Noord B.V. in de GWW, gepubliceerd op TenderNed. De inschrijving sloot op donderdag 29 oktober 2026 om 16:00 uur; deze aanbesteding is gesloten.
Uit onze inzichten
Data & praktijkVraag de Wet
Gratis · geen accountEen vraag over de aanbestedingsregels? Stel hem in gewoon Nederlands — u krijgt het antwoord met het wetsartikel erbij, en zonder bron geen antwoord.